Outdoor floor clamp fixation
2) Fixed floor 1: Place the first floor on the keel;
3) Insert the buckle: Push the buckle into the four slots on both sides of the floor;
4) Fixed floor 2: Weigh the other side of the cartoon buckle on the second floor;
5) Fixing clamp: fix the clamp on the keel with screw.
Precautions: Make sure the ground is flat, clean, dry, and capable of driving nails


Reserved seam clamp: 5-6mm for floor installation seam
1. Minimum configuration of keel
laying cement bricks below the keel.
2. Professional configuration of keel
Double layer keel laid on cement bricks,
Ensure long-term stability.
3. Recommended specification of keel (unit: mm):
Anticorrosive wooden keel: 40 * 60, 50 * 80 60 * 100
Galvanized steel keel: 40 * 40 * 3.50 * 3.50 * 100 * 3.
4. Specification for keel spacing
The spacing between regular paving keels shall not exceed 465mm, special load-bearing requirements, with additional keel according to the situation
5. Normal phenomenon
Conventional outdoor surfaces can weather under the influence of wind, rain, frost, and sunlight (ultraviolet). After a period of use, discoloration, slight cracks, and rough surface are all normal phenomena.
Installation method of floor nailing